We have started our project 'Stationoffices Almere' commissioned by Kroonenberg Group. Both station offices will be transformed into flats and raised by two layers.

Everything must be wind and watertight by the end of 2021, so that the municipality can redesign the public areas (with the aim of improving their appearance in preparation for the Floriade in Q2 2022). Total completion including completion of flats is expected in May 2022. 

At the same time, Central Station will be expanded and the station roof renovated: a major logistical challenge for all contractors involved!